第三章 技術性能及參數
Chapter 3 Technical Performance and Parameters
詳見訂貨合同要求及設備安裝總圖及裝配圖中的技術要求和參數。
For details, see the order contract requirements and the technical requirements and parameters in the equipment installation general drawings and assembly drawings.
第四章 基礎要求及供貨范圍
Chapter 4 Foundation Requirements and Scope of Supply
一.對基礎的要求
1. Requirements for the foundation
輥壓機可以安裝在地平面上,也可以安裝在樓板上,可以采用鋼筋混凝土基礎,也可采用鋼結構基礎。
The roller press can be installed on the ground plane or on the floor. It can be the reinforced concrete foundation or the steel structure foundation.
由于擠壓粉碎力全部在封閉的機架被平衡,故對基礎主要考慮其機身重量和水平,垂直動載荷系數。
Since the crushing force is fully balanced in the closed frame, the weight of the body and the horizontal and vertical dynamic load coefficients are mainly considered for the foundation.
1.主機重量按100噸考慮。若將主機基礎分為兩部分,其各需承受的重量可以按設備長度比例進行估算。
1. The weight of the main machine is considered as 100 tons. If the base of main machine is divided into two parts, the weight that each needs to bear can be estimated in proportion to the length of the equipment.
2.基礎的垂直動載荷系數,可以按1考慮。
2. The vertical dynamic load factor of the foundation can be considered as 1.
3.基礎的水平動載荷系數,可以按0.8考慮。
3. The horizontal dynamic load factor of the foundation can be considered as 0.8.
二.輥壓機配套供應范圍:
2. Supply range of roller press:
1.由生產廠家供貨的設備
1. Equipment supplied by the manufacturer
⑴主機本體(包括機架、軸承等七大部分)一套
⑴One set of main machine body (including seven parts such as frame and bearing)
⑵帶縮套聯軸器的行星減速器兩套
⑵Two sets of planetary reducer with shrink sleeve coupling
⑶萬向節傳動軸兩套
⑶Two sets of universal joint drive shafts
⑷高壓三相異步電動機(用戶可自購或委托制造商配套)
⑷High-voltage three-phase asynchronous motor (users can purchase by themselves or entrust the manufacturer to support them)
⑸主機微機控制柜
⑸Main machine computer control cabinet
⑹主電機控制柜3
⑹Main motor control cabinet 3
⑺附件: Ⅰ液壓蓄能器充氣工具一套
⑺Accessories: ⅠA set of charging tools for hydraulic accumulator
Ⅱ耐磨焊條10kg
Ⅱ Wear-resistant electrode 10kg
2.用戶自備設備
2. User-supplied equipment
⑴集中潤滑充填泵(手動或自動)
⑴ Centralized lubrication and filling pump (manual or automatic)
⑵扭力矩搬手(250~750Nm)及六角套筒M30、M20螺栓配套)
⑵ Torque handle (250~750Nm) and hexagon socket M30, M20 bolts matching)
⑶氮氣瓶兩只
⑶Two nitrogen bottles
⑷除鐵器(皮帶自卸式)
⑷Iron remover (belt self-unloading type)
⑸稱重倉及傳感器
⑸ Weighing bin and sensor
第五章 設備安裝前注意事項
Chapter 5 Precautions before Equipment Installation
一.設備的開箱檢驗
1. Unpacking inspection of equipment
輥壓機在生產過程中雖經過周密考慮,并在出廠交付裝運前已經過徹底的測試和完善的運前準備,但在運輸過程中可能導致機器的損壞。請對照裝運清單逐條進行仔細檢查。如發現有損壞或零部件短缺,請及時通報承運單位。
Although the roller press has been carefully considered during the production process, and has been thoroughly tested and perfect pre-shipment preparation before delivery and shipment, it may cause damage the machine during transportation. Please check carefully one by one against the shipping list. If any damage or shortage of parts is found, please notify the carrier in time.
設備到貨后,使用廠方及時會同制造廠對所到貨物和隨機文件進行清點、驗收,辦理移交手續。所有貨物須登記上冊入庫、文件建檔;對于缺損的貨物要求制造廠及時補齊,技術文件做好發放登記工作。
After the equipment arrives, the user and the manufacturer shall check and accept the goods and random documents in time with the manufacturer, and go through the handover procedures. All goods must be registered and put into the warehouse, and the documents shall be filed; for the defective goods, the manufacturer shall be required to fill up in time, and the technical documents shall be issued and registered.
二.設備的裝卸
2. Loading and unloading of equipment
貨物到達現場后的裝卸和搬運應按下面的要求進行:
The loading, unloading and handling of goods upon arrival at the site shall be carried out according to the following requirements:
1) 首先組織有關人員制定卸貨和運輸方案,清理好庫房和露天貨場,根據貨場種類、編號、安裝順序統一安排存放地點,力求減少搬運次數。
1) First, organize relevant personnel to formulate unloading and transportation plans, clean up warehouses and open yards, and uniformly arrange storage locations according to yard types, numbers, and installation sequences, and strive to reduce the frequency of transportation.
2) 認真做好具體工作人員的技術培訓和安全教育工作。
2) Do a good job in technical training and safety education for specific staff.
3) 準備好各種適應的起吊和運輸設備工具等。
3) Prepare all kinds of suitable lifting and transportation equipment tools.
4) 對于需要小心謹慎裝卸的貨物,在搬運和起吊作業中應根據貨物的包裝標記及要求進行。
4) For goods that need to be carefully loaded and unloaded, handling and lifting operations should be carried out according to the packaging marks and requirements of the goods.
5) 卸貨前要認真檢查火車(汽車、船)上各貨物捆綁和裝車方法,確保在移動捆綁材料時不致引起貨物的損壞。
5) Before unloading, carefully check the binding and loading methods of each cargo on the train (car, ship) to ensure that the cargo will not be damaged when the binding materials are moved.
6) 要認真熟悉設備的裝箱單及其要求,按設備的總裝箱單所分解的包裝單元。做到文明卸貨、輕吊、輕放,不準隨意扔摔。
6) Familiarize yourself with the packing list of the equipment and its requirements carefully, and decompose the packing unit according to the equipment packing list. Do the unloading, lifting and handling in the civilized manner, and are not allowed to throw them at will.
7) 在裝卸作業中,應避免貨物與貨物之間,貨物與運輸工具之間,貨物與其他建筑物之間的磕碰現象,不得損壞油漆表面、加工表面,必要時應加木墊或其他軟墊,鋼絲繩應加膠套或使用專門的吊裝工具。
7) During loading and unloading operations, collisions between the goods and the goods, between the goods and the means of transport, and between the goods and other buildings should be avoided. The painted surface and the processed surface should not be damaged. If necessary, wooden mats or other soft cushions should be added, and steel wire ropes should be covered with rubber sleeves or use special lifting tools.
8) 起吊作業注意事項:
8) Precautions for lifting operation:
吊繩應拴掛在標有起吊標記的地方。對于加工表面用木料襯托等保護的貨物,為了防止損傷,吊繩應拴掛在襯托處。
The sling should be tied to the place marked with lifting mark. For goods protected by wood lining on the processed surface, the sling should be tied to the lining in order to prevent damage.
無起吊標記時,吊繩應掛在設備適當的部位,應先試吊,找好重心方能起吊, 嚴防損傷設備和發生事故。
When there is no lifting mark, the lifting rope should be hung on the appropriate part of the equipment, and the lifting should be tested first, and the center of gravity can be found before lifting, so as to prevent damage the equipment and accidents.
9) 利用其他運輸工具作業時應按照各有關規定進行裝運作業。
9) When using other means of transportation to operate, carry out shipping operations in accordance with relevant regulations.
10) 對于要求保持干燥和室內儲存的貨物遇有陰雨天氣時應停止作業,蒙好氈布看管起來。
10) For the goods that are required to be kept dry and stored indoors, the operation should be stopped in case of rainy weather and covered with blankets.
11) 貨物在搬運過程中,應有完善的固定措施,嚴防在運輸過程中發生滾動或滑動,以免發生設備的損傷或事故。
11) During the transportation of the goods, there should be perfect fixing measures to prevent rolling or sliding during transportation to avoid equipment damage or accidents.
三.設備的貯存
3. Equipment storage
貨物到達現場后,存放和安裝間隔一段時間,為了防止設備在這段過程中銹蝕或損壞,避免安裝時出現故障和困難,因此對貨物的存放和保管提出下列要求:
After the goods arrive at the site, there is a period of time between storage and installation. In order to prevent the equipment from rusting or damage during this process, and to avoid failures and difficulties during installation, the following requirements are put forward for the storage and custody of the goods:
1) 無論室內、室外存放,也無論包裝形式如何,所有貨物都應放在木枕上。避免貨物與地面直接接觸,貨物底部離開地面的高度不得小于 150 毫米。
1) Regardless of whether it is stored indoors or outdoors, and regardless of packaging, all goods should be placed on wooden sleepers. Avoid direct contact between the cargo and the ground, and the height of the bottom of the cargo from the ground should not be less than 150 mm.
2) 存放貨物選擇在排水、通風良好,無有害氣體的地方。
2) Store goods in a place with good drainage, good ventilation and no harmful gas.
3) 室外存放,如果使用棚布覆蓋,雨后應及時處理,以防棚布上積水并應注意通風,保持干燥。
3) For outdoor storage, if you use shed cloth to cover, you should deal with it in time after rain to prevent water from accumulating on the shed cloth and pay attention to ventilation and keep it dry.
4) 對于鋼結構件,吊裝安放時要小心,嚴禁扭彎,要按照有關要求放于枕木上。
4) For steel structural parts, be careful when hoisting and placing them, twisting is strictly prohibited, and they must be placed on sleepers in accordance with relevant requirements.
5) 對于一般機械的加工表面,螺紋等應按要求涂防銹油膜。
5) For the machined surface of general machinery, thread etc. should be coated with anti-rust oil film as required.
6) 所有貨物在裝卸、運輸、入庫過程中遇有油漆剝落,應及時按要求修整補涂。
6) Paint peeling off all goods during loading, unloading, transportation, and storage, should be repaired and repainted in time as required.
7) 保管期間內每月一次,檢查各包裝件有無異常現象,發現問題及時處理。保管過程中,每半月進行抽檢,并做好檢驗記錄。特別是遇異常天氣,臺風及雨季時,更需注意保管。
7) Once a month during the storage period, check each package for abnormalities, and deal with any problems in time. During the storage process, random inspections are conducted every half month and inspection records are made. Especially in the event of abnormal weather, typhoon and rainy season, it is necessary to keep it safe.
8) 橡膠板,密封圈,各種電纜應避免直接受太陽照射。
8) Rubber plates, sealing rings, and various cables should be protected from direct sunlight.
9) 倉庫的存放和保管
9) Storage and custody of warehouse
倉庫是具有防雨雪、風沙、潮濕的設施。要確保通風良好,無水浸蝕。如果要把貨物堆積起來,原則上堆積的層數不得超過二層。大件在下層,小件在上層,兩層之間用木墊隔開。
The warehouse is protected from rain, snow, wind and sand, and humidity. Ensure good ventilation and no water erosion. If the goods are to be piled up, in principle, the number of layers should not exceed two. The large pieces are on the lower layer and the small pieces are on the upper layer. The two layers are separated by wooden mats.
墊木長度不短于下箱。應做到大不壓小,重不壓輕。當通過計算和其他方法確認對下層貨物無損傷的情況下,根據需要也可堆成三層。重量大于3 噸的包裝箱和物體不應堆積存放。貨物的存放,要把標牌的一面面向通道,便于查找。電氣設備和控制設備(包括各種保護裝置的電氣控制開關)均應存放在專門的庫房里,要保證溫度和濕度的要求。液壓、潤滑油站和控制閥件應儲存在相對干燥、溫度無劇烈變化的場所。貨物經開箱后,再要入庫存放時,要把它恢復到開箱的狀態。
The stow length is not shorter than the lower box. Should be big and not overwhelming, not overweight. When it is confirmed by calculation and other methods that there is no damage to the underlying cargo, it can be stacked into three layers as needed. Packing boxes and objects weighing more than 3 tons should not be stacked and stored. For the storage of goods, one side of the sign should face the passage for easy searching. Electrical equipment and control equipment (including electrical control switches for various protection devices) should be stored in a special warehouse to ensure temperature and humidity requirements. Hydraulic and lubricating oil stations and control valves should be stored in relatively dry places with no drastic changes in temperature. After the goods are unpacked, they must be restored to the unpacked state when they are put into inventory.
10) 簡易庫房的存放和保管
10) Storage and custody of simple warehouse
簡易庫房的地面需要重新平整,房頂和四壁要臨時遮蓋。陽光、風雨等不能進入。貨物的放置應具有良好的通風條件。嚴密注視地面的積水并及時疏通排泄.對已受潮貨物應及時處理。
The ground of the simple warehouse needs to be leveled again, and the roof and walls should be temporarily covered. Sun, wind and rain cannot enter. Goods should be placed with good ventilation conditions. Pay close attention to the accumulation of water on the ground and clear the drainage in time. Deal with the damp goods in time.
11)露天貨場的存放和保管
11) Storage and custody of open yard
露天貨場應設置在灰塵少,蒸汽少,通風良好的地方。需要用帆布覆蓋保護的貨物,即使是運輸中臨時存放或已經防腐處理好的設備和材料,仍需用防護帆布覆蓋保護。用防護覆蓋貨物時應注意,放置設備的鋼結構凸出部分或邊緣部分將帆布刮破。經常檢查貨物表面油漆是否起皮或脫落,加工表面是否銹蝕,結構件是否發生扭曲變形等異常情況,發現問題要及時處理,并要清除隱患,以確保產品質量不變。
The open-air cargo yard should be set up in a place with less dust, less steam and good ventilation. Goods that need to be covered with canvas, even if the equipment and materials are temporarily stored during transportation or have been treated with anti-corrosion treatment, still need to be covered with protective canvas. When covering the cargo with protection, be careful that the projecting part or edge part of the steel structure where the equipment is placed will scratch the canvas. Frequently check whether the paint on the surface of the goods is peeling or peeling off, whether the processed surface is corroded, whether the structural parts are distorted or deformed, etc., and if any problems are found, they must be dealt with in time and hidden dangers must be removed to ensure that the product quality remains unchanged.